Skip to main content
Applications
Applications · LRI AEM-60DC8

DC supervision in power substations

DC auxiliary monitoring of LV/MV substations with AEM-60DC8. IEC 61850, critical cybersecurity, blackout prevention and Secure by Design.

LRI Engineering2026-05-269 min

The problem

Power substations — LV, MV and HV — depend on the DC auxiliary system (typically 110, 125 or 220 VDC) to feed protection relays, breaker controls, signaling and telecontrol. A failure in the DC auxiliary leaves the substation blind and unable to operate, and the worst operational scenario is exactly the extended blackout in which the DC system is most demanded. Operators face three combined pains: (1) battery banks that age silently between scheduled discharge tests; (2) growing cybersecurity requirements in substation automation (IEC 61850 + IEC 62443) that make measurement IEDs an audit target; and (3) integration with legacy systems that expect open protocols without expanding the attack surface. The result is a demand for dedicated DC supervision, with continuous telemetry and clear segregation between measurement and protection.

Voltage range. The AEM-60DC8 measures 0 to 60 VDC per channel. 110 and 125 VDC banks and buses use the AEM-150DC8 model (0 to 150 VDC), listed in the datasheet of the same family; 220 VDC auxiliary service is outside the range of both models and is not covered by this application. The examples below use the AEM-150DC8 for 110 VDC, with typical accuracy of ±1% FS (about ±1.5 V at 150 V, approx., extrapolated from the ±1% FS).

Golden rule: substation without dedicated DC visibility walks on invisible risk surface.

Typical topology

A typical substation has a DC system consisting of a charger (rectifier), a stationary lead-acid battery bank (54 to 108 cells depending on voltage) or nickel-cadmium, main DC bus and sectorized distribution to protection, control and telecontrol cubicles.

AC auxiliary service
       |
       v
+---------------+      +-----------------+
| Charger       |  DC  | Battery bank    |
| (rectifier)   |----->| Pb-acid or NiCd |
+---------------+      +--------+--------+
       |                        |
       v                        |
   Main DC bus  +---------------+
       |
       +------> Protection panel (relays)
       +------> Breaker control
       +------> Telecontrol (RTU/IED)
       +------> Signaling

Sensing:
       |
       v
   +-----------+
   | AEM-60DC8 | --- Modbus RTU ---> IEC 61850 gateway
   |   x N     |                    (SEL-3530, MGate)
   +-----------+

The AEM-60DC8 sits on a segregated RS-485 network separated from the station network, and the gateway translates to MMS/GOOSE at the substation level.

Golden rule: measurement on segregated network — protection on 61850 network — never mixed.

What to measure and why

In substation DC systems, these quantities are priorities. The AEM-150DC8 (and the AEM-60DC8, up to 60 VDC) measures DC voltages and temperature through a single NTC; current and ground isolation are outside the scope of the device:

Quantity Justification
Main DC bus voltage (V) Confirms operation within range (e.g., 105–137 VDC for a 110 VDC bank); reference for all fed IEDs.
Block voltage per battery (V) In a 54-block bank of 2 V, reading is done by block group (see sizing). With typical accuracy of ±1% FS, deviations of tens of mV between blocks are not resolved.
Bank temperature (deg C) Useful life drops 50% per 10 deg C above 25 deg C; thermal compensation essential.

In new substations with LiFePO4 banks (growing trend since 2024), block voltage is replaced by reading via dedicated BMS, leaving the AEM-60DC8 to read aggregate bus and sector quantities.

Golden rule: the DC bus voltage is the base quantity — choose the model (60 or 150 VDC) from the bank nominal voltage.

Sizing — how many AEM-60DC8?

Formula:

N_AEM = ceil( (V_bus + n_monitored_groups + n_outputs) / 8 )

Simplified example for MV substation with 54-block lead-acid bank (110 VDC), aggregated monitoring (bank in 6 groups), with AEM-150DC8:

  • Bus voltage: 1 channel
  • 6 block groups: 6 channels
  • 4 sectorized outputs: 4 channels
  • Bank temperature: 1 dedicated NTC (does not use a channel)
  • Total: 11 channels → 2 AEM-150DC8 (8 channels per unit)

Golden rule: 220 VDC banks are outside the range of the AEM-60DC8 and AEM-150DC8; do not size them with these models.

Recommended setpoints and alarms

Reference values for 110 VDC DC system, 54-block lead-acid bank:

Variable Warning Critical Automatic action
Bus voltage (V) <108 or >135 <105 or >137 Notify control center; generate 61850 event
Bank temperature (deg C) >30 >40 Reduce float current

Golden rule: validate alarm bands against the bank band (e.g. 105–137 VDC) and the ±1% FS resolution of the model.

SCADA / PLC integration

Integration between AEM-60DC8 and IEC 61850 environment follows the gateway pattern:

Schweitzer SEL-3530 RTAC: configure the AEM-60DC8 as a Modbus Serial Slave. The RTAC translates to IEC 61850 Logical Nodes (MMS), typically MMXU for electrical quantities. Suggested polling: 1 s for critical voltages, 5 s for temperature.

MOXA MGate 5119: Modbus RTU to MMS/GOOSE gateway with web configuration. Recommended for smaller substations.

AVEVA System Platform: with a hierarchical DC_System object (Substation → DC_Bus → Battery → Block), allows navigation via PowerSCADA. Natively compatible with IEC 61850.

Elipse Power: uses IODriver-Modbus driver for the AEM-60DC8 and IEC 61850 driver for the main IEDs, keeping a segregated architecture by design.

Siemens SIPROTEC or ABB REF PLCs: indirect reading via gateway, without mixing protection and measurement traffic.

See whitepaper WP03 with IEC 62443-4-2 checklist applicable to substations.

Golden rule: DC measurement never shares a network with GOOSE — design segregates or you pay during an incident.

Regulatory compliance

Power substations follow hierarchical requirements in Brazil:

  • ONS Grid Procedures (Module 2.6 — Measurement equipment), submodules relating to substations
  • ONS REN-01 (Cybersecurity requirements for operation)
  • ABNT NBR 5419 (lightning protection, applicable to grounding)
  • IEC 61850 (substation automation communication)
  • IEC 62443-4-2 — AEM-60DC8 aligned, without formal certification, for the equipment
  • IEEE 1188-2005 and IEEE 1115 (maintenance and selection of stationary batteries)
  • ANEEL PRODIST Module 8 (power quality, HV/MV context)

For utilities under ONS, the AEM-60DC8 immutable forensic telemetry contributes to evidence in post-event analysis.

Golden rule: standards are floor; cybersecurity audit demands proof, not promise.

Illustrative case

Simplified example: a distribution utility operated 47 MV substations in the state of Santa Catarina, with 110 VDC DC system and 54-block lead-acid banks. After two incidents in 18 months (a maneuver loss during a storm and a protection failure attributed to DC bus drop), the operator specified dedicated DC supervision in 12 substations classified as critical.

Implementation (illustrative): 2 AEM-150DC8 per substation monitoring bus, 6 block groups, 4 sectorized outputs and bank temperature (NTC). Integration via SEL-3530 RTAC to the central SCADA with PI System expansion.

Result: example without field data. The expected gain is continuous visibility of bus, group and output voltages, within the ±1% FS resolution (about ±1.5 V at 150 V, approx., extrapolated from the ±1% FS).

Golden rule: instrumenting before the incident is always cheaper than justifying it afterwards.

Deployment checklist

  1. Survey DC topology (nominal voltage, number of blocks, chemistry, sectorized outputs).
  2. Define monitoring level (aggregated, per group, per block) and justify by criticality.
  3. Choose the model from the bank nominal voltage (AEM-60DC8 up to 60 VDC; AEM-150DC8 up to 150 VDC); 220 VDC is out of range.
  4. Compute N_AEM and reserve 2 channels per unit for expansion.
  5. Place AEM-60DC8 in a dedicated cubicle, segregated from the 61850 network.
  6. 22 AWG shielded twisted-pair cable, shield grounded at a single point.
  7. Configure Modbus → IEC 61850 gateway and map holding registers.
  8. Define Slave IDs and baudrate 19200 bps on the RS-485 bus.
  9. Validate 147 holding registers and enable forensic telemetry.
  10. Document post-commissioning baseline and record in asset management system.

Golden rule: substation without commissioning baseline is history that starts from zero every team handover.

FAQ

See the FAQ block in the frontmatter of this page.

Related content

More LRI technical materials on adjacent topics.